|
|
|
Quick Links: |
|
Introduction Two HVS experimental concrete sections were constructed near Hilton, approximately mid-way between Pietermaritzburg and Howick, adjacent to the N3. The scope of the study is to investigate the effect of the following variables in the concrete on load transfer at a crack over time: Joint type: Aggregate type: To concrete test sections were constructed as follows: A PCC section containing 26 mm dolerite stone, with 6 plain/aggregate interlock joints and 6 dowelled joints; and |
Figure 1: Cross-section of pavement structure |
Pavement Structure of Trial Sections A cross-section of the pavement structure is given in Figure 1 above. The selected and subbase layers were constructed with weathered granite material of G5 quality to increase the stress at the joints and thus to enhance early failures. Layout of Concrete Trial Sections Each HVS test is done on an 8 m section. This means that if a standard 4 m-panel length is used; two joints are tested. By appropriately positioning the HVS, the full length of the mid panel (4m in length) together with half of the lengths of the adjacent panels are tested in each HVS test. Thus, to conduct two HVS tests per variable, a minimum of six 4 m-panels were required. In addition, panels had to be provided at the beginning and the end of each test section to serve as a uniform foundation on which to position the HVS (see Figure 2). Crack inducers (45 mm x 3 mm steel plates) were cast into the concrete at 4 m intervals at the bottom of the slabs to form aggregate interlock cracks at the predetermined positions. For the doweled joints R20 dowels at 300 mm spacing supported on 65 mm x 3 mm steel plates were placed at the bottom of the slab. Along the plain aggregate interlock joints, the dolerite aggregate concrete slab has cracked in only two joint positions and along the doweled joint section, it has cracked in only one joint position. Along the plain aggregate interlock joints, the quartzite aggregate concrete slab has cracked in one place, approximately 300 mm off a joint and along the doweled joint section; it has cracked in only one joint position.
|
|
|
Figure 2: Schematic layout of trial sections
|
|
Construction Techniques The layer works for the concrete slabs were constructed with standard construction equipment. No special techniques were required. The subbase had to be constructed to strict level tolerances in order to create a sound working platform for the concrete. The shuttering and joint formers were put up as can be seen from Photo 1, with special strain gauges on custom made brackets for measuring shrinkage at the cracks (Photo 2). The concrete was delivered to site in rotating drum mixers and poured into the shuttering with a chute (Photo 3). The concrete was then levelled by hand (Photo 4), compacted with poker vibrators and levelled with a wooden float (Photo 5). The concrete surface was treated with a white-coloured resin based (Resincure HW) curing compound, after finishing (Photo 6).
|
|
Photo 1: Shuttering for dolerite concrete section complete with joint formers for aggregate interlock joints – dowel cages in background
Photo 2: Aggregate interlock joint former and shrinkage measuring devices
Photo 3: First concrete pour
Photo 4: Hand-levelling of concrete
Photo 5: Levelling the concrete
Photo 6: Completed concrete slabs
|
|
Deflection Testing Falling Weight Deflectometer (FWD) testing was conducted during October 2003. On both concrete test sections, tests were done across each joint position in both wheel tracks. The relative movement calculated across each joint position, is indicated in Figure 3. |
|
Figure 3: FWD relative movement across joint positions |
|
In the direction east to west, the concrete cracked close to joint number 3 and at joint number 7 on the quartzite concrete section. Similarly, the dolerite concrete section cracked close to joint number 2 and at joints number 4 and 7. From Figure 3 it is obvious that increased relative movements occurred where the concrete was cracked. Preliminary ResultsHVS testing of the concrete pavement trial sections commenced on 2 November 2003 across an aggregate interlock joint in the quartzite aggregate concrete slab. Pumping of the subbase material through the joint was visible after 7 700 load repetitions and to the side of the slab after 40 400 load repetitions of a 40 kN dual wheel (see Photos 7 and 8).
|
|
Photo 7: Pumping of subbase material through aggregate interlock joint after 7 700 load repetitions
Photo 8: Pumping of subbase material at side of aggregate interlock joint after 40 400 load repetitions
|
|
Preliminary results of this first test indicate a strong linear relationship exists between the loads applied and the relative movement between the two slabs at the joint; with an increase in relative movement with increasing load repetitions (see Figure 4).
|
|
Figure 4: Relative movement across aggregate interlock joint in quartzite aggregate concrete slab
|
|
General Activities Data capturing, validation, processing and analysis are ongoing activities during the test programme, and the output data will be incorporated into a first-level output report. A project management group, consisting of the Research Project Manager, the HVS Project Engineer and the HVS Operational Manager are responsible for the day-to-day technical management of the project. Monthly site meetings are held to discuss progress, as well as technical and operational issues: Weekly progress reports, summarising the key issues for the client, are prepared. The HVS Technician compiles this report from data provided by the HVS Operator and it contains the following information: date, week number, section number, wheel load, tyre pressure, repetitions for the week and total repetitions for the section, water applications, weather details, machine productivity with a summary of operational times, pavement condition deterioration, measurements taken and scheduled, progress according to plan. A monthly report is presented at the monthly technical meeting. The Client, the CSIR Project Manager, the Research Manager, the HVS Project Engineer and key members of the project team are invited to attend this meeting. A first-level analysis report will be compiled when all testing has been completed and data captured. It will provide a summary of the measurements taken, test interventions and behaviour. The HVS Project Engineer will prepare the report with assistance provided by the HVS Operational Manager, reviewed by the Research Manager and approved by the CSIR Project Manager before being disseminated. A second-level analysis report will be compiled on completion of the investigation. It will summarise the experimental design, relationships between laboratory test results and HVS test results, amongst others, data analysis and the findings. Ways of implementing the findings will be recommended. The Research Manager will prepare the report with assistance from the HVS Project Engineer and the CSIR Project Manager, in consultation with an industry task group. The outcomes of the study will be disseminated to industry. A series of courses will be held under the auspices of C&CI. Feedback will also be provided at the RPF meetings. |
|
| <<<<< Back to Top | |
Home | Background Info | History | Technical info | HVS documents | Instrumentation | APT facilities | Recent testing| Contact us Copyright © 1968-2002 All rights reserved • Webmaster |
|